PROJECT PHASE PLAN:
The teams are requested to present their project phase plans. The generic plan is listed below; it consists of five phases. Successful completion of each phase is worth 10% towards the final mark in the course.
Each team is free to propose a modified phase plan, together with the team marking scheme. Such plans are subject to approval by the course instructor.
GENERIC PROJECT PHASE PLAN:
Definition Phase (Identification of Requirements)
- Primary Objectives:
- Specification of requirements
- Preliminary project plan
- Definition of acceptance criteria
- Secondary Objectives:
- Finding people
- Understanding the development environment
- Forming tentative design ideas
Design Phase
- Primary Objectives:
- Baseline design of operational software
- Baseline design of support software
- Secondary Objectives:
- Preparation for integration testing
- Setting up change controls
- Constructing simulation models
- Planning manpower for subsequent phases
- Preparation for programmer training
- Publication of Programmer's Handbook (coding standards, naming conventions, etc.)
- Initial preparation for systems test
- Initial preparation for acceptance test
- Initial preparation for site test
- Setting up project libraries
Development Phase
- Primary Objectives:
- Detailed design
- Coding
- Module test
- Integration test
- Software documentation
- Secondary Objectives:
- Detailed preparation for system test
- Detailed preparation for acceptance test
- Detailed preparation for site test
- Preparation for customer training
System Test Phase
- Primary Objectives:
- Testing against Specification of Requirements
- Testing as "live" as possible
- Testing not controlled by programmers
- Secondary Objectives:
- Completion of acceptance test preparations
- Customer training
- Correction of descriptive documentation
- Completion of user documentation
- Re-assignment of people
Acceptance Phase
- Primary Objectives:
- Execution and analysis of acceptance tests
- Signing of formal acceptance agreement
- Assistance in installing the system
- Assistance in beginning operation
- Secondary Objectives:
- Completion of customer training
- Cleanup of documentation
- Testing on-site
- Continuing maintenance and tuning
- Continuing operation
- Project evaluation
REFERENCE:
After P.W. Metzger: Managing a Programming Project, 2nd ed., Prentice-Hall Inc., 1981, ISBN 0-13-550772-3